"After some extensive studies, it was determined that this would be a good candidate for Montana's first DDI. And it's due to the congestion that's been happening here for the last several years," MDT engineering project manager Shane Johnson told KULR8 this fall. The interchange he means is Exit 455 on I-90. For most of Lockwood, that exit is how you get onto the interstate, and it is also where the Town Pump travel stops sit.
The Montana Department of Transportation announced on October 23, 2026 that Riverside Contracting Inc. won the contract to turn the Johnson Lane Interchange into a diverging diamond. Utility relocation is already underway, and major construction is expected to start in spring 2027. KULR8 reports that MDT expects the work to wrap up in summer 2029. That means three construction seasons at the busiest corner in Lockwood. Since July 2025, Lockwood has also had a second route across the Yellowstone River, and it starts at Coulson Road.
What a diverging diamond does at Exit 455
A diverging diamond shifts traffic briefly to the left side of the road as it passes under or over the interstate. Drivers turning onto an on-ramp then make their left turn without crossing oncoming traffic. MDT's release says the layout cuts down the number of points where vehicles' paths cross. It also says the pattern may feel unfamiliar at first, so signals, signs and pavement markings will guide drivers through.
The problem MDT is targeting is the ramp backups. "The biggest benefit is traffic queuing and backup up on the ramps back into the interstate," Johnson told KULR8. He added that the same thing happens at a couple of other Billings interchanges. MDT and its engineering firm DOWL have posted a video simulation of traffic moving through the new interchange. It's the fastest way to see the left-side crossover before you drive it.
Beyond the interchange itself, MDT lists roadway improvements on North Frontage Road, Old Hardin Road, Cole Street and Becraft Lane. It also lists new traffic signals at Cole Street and Old Hardin Road and at Johnson Lane and North Frontage Road, sidewalk and ADA upgrades on nearby streets, and a shared-use path through the interchange for people walking and biking. Until now, crossing I-90 at Johnson Lane on foot or by bike has meant using the same lanes as freight traffic. A dedicated path across the interstate is new for this side of Lockwood.
The order of the work, season by season
MDT has said which part of the interchange gets rebuilt first, and that order tells you which part of your routine will feel it first.
| Construction season | What MDT plans |
|---|---|
| Fall 2026 | Relocation of select underground utilities, already underway |
| First season, starting spring 2027 | Rebuilding the I-90 bridges over Johnson Lane, with improvements south of I-90 finished first |
| Second season | Work north of the interstate, with the bridge work continuing |
| Third season | Final pavement treatments across the project, with completion expected in summer 2029 |
The I-90 bridges have to be widened because a diverging diamond needs more roadway width than the current layout. That bridge work runs through the first two seasons. MDT has told KULR8 that business access will stay open throughout, and that drivers should expect traffic patterns to change as the work moves along.
Those changing patterns will reach the everyday stops around the exit. Lockwood IGA is at 1960 Old Hardin Road, the same road listed for improvements and a new signal at Cole Street. The Pilot/MT Lil's travel stop, which has a McDonald's inside, and the Flying J/Lucky Lil's both sit at Exit 455 itself. We wrote about Old Hardin Road as Lockwood's everyday corridor in Lockwood Doesn't Have a Downtown. It Has Old Hardin Road., and the next three seasons will rebuild the end of it nearest the interstate.
Lockwood already has a second crossing
Johnson Lane is also where the Billings Bypass is supposed to begin. MDT describes the bypass as a six-segment arterial running from the Johnson Lane Interchange north across the Yellowstone River to the Old Highway 312 and US 87 intersection in the Heights. As of 2026, three of the six segments are complete. Five Mile Road was rebuilt and extended to Old Highway 312 with a roundabout. The Yellowstone River Bridge was finished in fall 2022, with two travel lanes each way and a 10-foot shared-use path. The Railroad Overpass bridge was completed in 2025.
The pieces that would join the new road to Johnson Lane haven't been built yet. To let people use the river crossing in the meantime, MDT installed a temporary connection from the new roadway, now officially named NE Billings Bypass, to Coulson Road. The Yellowstone County News reported the opening date as July 3, 2025. MDT's directions at the time, quoted by KULR8, were specific. Through traffic from Lockwood uses the existing Coulson Road on the west side. Through traffic from the Heights comes in by Old Highway 312 and Five Mile Road. Mary Street and Dover Road are for local access only.
For a Lockwood household headed to the Heights, that puts a river crossing on the map that doesn't run through Exit 455 or the older roads through town. Mike Taylor, MDT's district administrator, said shortly before the July 2025 opening that the bypass should "hopefully shorten their commute to and from wherever they're going and take some of that pressure off of Heights and Main Street," according to KULR8. The City of Billings' Heights Neighborhood Plan, dated July 2026, lists congestion on Main Street and Wicks Lane as a resident concern. It expects new connections, including the bypass and Skyway Drive, to move some of that traffic.
The congestion at Exit 455 is not new. In a 2021 KTVQ story about Lockwood's hopes for the bypass, a local trucking business said traffic regularly backed up around the Johnson Lane interchange.
Where the two projects meet
The interchange rebuild and the river crossing are two halves of the same road. Segment 5 is the stretch from the Johnson Lane Interchange to the Railroad Overpass. It is in final design and right-of-way acquisition, and MDT tentatively puts construction in 2028, depending on when design is finished. Once that segment is built, the bypass will run straight from the new diverging diamond to the river bridge, and the Coulson Road connection will no longer be the way in. At the north end, Segment 6, from Five Mile Road to US 87, is also in design and tentatively scheduled for construction in 2030.
Johnson Lane is the most expensive piece. MDT's Billings Bypass FAQ lists the interchange at about $78.1 million of a roughly $158.8 million estimated total. That compares with $32.5 million for the Yellowstone River Bridge, $19.5 million for the Railroad Overpass and about $8.1 million for the Segment 5 connector. MDT says funds have been identified for the whole project. In its July 1, 2025 report on the partial opening, KTVQ put the total at $136 million. The FAQ table is the more recent estimate.
Taken together, the schedule looks like this. Starting in spring 2027, the south side of Exit 455 comes first and the north side follows in the second season, with the connector to the river bridge tentatively set for 2028. Today, the way onto the bypass from Lockwood is the Coulson Road connection to Five Mile Road and Old Highway 312.
You can follow it as it happens. MDT sends construction updates by text if you text BBP to 833-648-0322. Its project team answers questions at [email protected] and 406-294-9668, and the Johnson Lane Interchange page is where the alerts and the simulation live. We'll keep covering Lockwood on our Lockwood neighborhood page.
If you live near Exit 455 and are wondering how three seasons of work around Johnson Lane, Old Hardin Road and Cole Street could affect a sale or a purchase you're planning, our team at Huskey Real Estate Group can walk through the timing with you. Schedule a Consultation, and we'll talk through how the Johnson Lane schedule lines up with your plans.